What Is an Easement? How It Affects Building and Renovating in Victoria

By :
November 13, 2026
Site plan showing an easement along the rear boundary of a Melbourne block

An easement is a legal right for someone else, such as a neighbour, council or water corporation, to use part of your land for a specific purpose like drainage, sewerage or access. You still own that land, but you cannot build over it or block it without consent.

For anyone building or renovating in Victoria, that strip of land can decide where the house, garage, pool or extension goes, how the footings are designed and how long approvals take. This guide explains what an easement is, how to find one on your title, how it shapes a design, and what it takes to build over, vary or remove one.

What an easement is

An easement gives a person or authority the right to use land owned by someone else for a specific purpose. According to LANDATA, Victoria’s title search service, easements do not change who owns the land, but they can limit what the owner does on the affected part, such as blocking access or interfering with the use the easement allows.

In plain terms, there are two sides to every easement:

  • The burdened land: the lot the easement runs across, which is often your block.
  • The benefited party: the neighbour whose lot gains access or drainage, or an authority such as a council or water corporation that holds the right for its pipes and cables.

Where the right belongs to an authority rather than a neighbouring lot, Land Use Victoria calls it an easement in gross. Sewer and drainage easements held by water corporations and councils are typical examples.

An easement stays with the land. When the property is sold, the new owner takes it subject to the same easement, which is why checking for easements before you buy matters as much as checking before you build.

Common types of easement in Victoria

Diagram of three neighbouring lots showing rear drainage, a sewer line and shared carriageway access
TypeWhat it allowsWho usually holds itWhat it means for building
Drainage (stormwater)Stormwater pipes or overland flow across the lotCouncilCouncil consent needed to build over it
SewerageSewer mains and connectionsWater corporationWater corporation consent needed near or over the pipe
Water supplyWater mainsWater corporationAs for sewerage
Carriageway or right of wayPassage on foot or by vehicle to another lotNeighbouring owner, sometimes councilThe way must stay open and usable
Electricity, gas, telecommunicationsCables, lines and pipesThe relevant utilityThat utility’s consent and clearances apply
Implied easementDrainage or services needed for neighbouring lotsNeighbouring owners or the authorityMay not appear on title at all

Drainage and sewerage easements are familiar constraints on residential blocks. In many Melbourne suburbs they run along rear or side boundaries, carrying pipes that serve several lots. Carriageway easements also occur on battle-axe blocks and properties with shared driveways.

Implied easements deserve a special mention. Under section 12(2) of the Subdivision Act 1988, easements for drainage and similar services can be implied in a plan of subdivision rather than drawn on it. The City of Ballarat notes that their scope cannot be found from a title search, so a block can carry obligations that are not visible on the title.

How to find easements on your property

Start with the title and the plan. A title search shows the registered interests on the land, and the copy of plan, available through LANDATA, shows where each easement sits, its width and its purpose. If you are planning a knock down rebuild in Melbourne, this is one of the first documents your builder and designer should look at.

Next, find where the pipes actually run. The easement on the plan marks a legal corridor, but the pipe inside it may not sit where you expect. Water corporations sell property asset plans and publish online asset maps. Yarra Valley Water, for example, offers both, showing current and proposed sewer and water locations.

Then allow for what the title will not show. Implied easements and older council drains can affect a block without a clear line on the plan. Glen Eira City Council notes that council can protect its drains even where no easement exists, and asks owners to apply as if one did.

If you are buying, have your conveyancer or lawyer review the title documents and plan in the contract of sale before you sign. Easements belong at the top of any pre-construction checklist for a custom build, because a design drawn without them usually has to be redrawn.

How an easement shapes your design

Pergola built clear of a marked sewer easement with the maintenance hole left accessible

An easement is a fixed line the design has to respect, and on a tight Melbourne block it often decides the layout. The questions a builder works through early are:

  • Where the house sits: habitable rooms are generally kept off easements, which can push the footprint forward or sideways.
  • Garages, carports and sheds: lighter structures are more often allowed over an easement, with conditions.
  • Pools and outdoor living: pools and spas are usually kept clear, which affects backyard planning.
  • Eaves and overhangs: small projections may be allowed where full rooms are not.
  • Access: pits and maintenance holes must stay reachable.

One council’s guidelines show how this works in practice. The City of Kingston’s Building Over Easement Guideline (effective 24 December 2024) supports certain structures subject to assessment and consent, including garages, carports and sheds less than 9 metres long, pergolas, decks, fences, eaves projecting less than 600 mm, and steps.

Kingston does not allow habitable rooms, basements, pools and spas, underground rainwater tanks, aboveground rainwater tanks larger than 3 kL, or structures over easements containing council stormwater pipes larger than 450 mm. Its guideline also excludes sheds and garages over 9 metres long.

Those are Kingston’s rules. Other councils and water corporations set their own, so the design has to be checked against the authority that holds your easement. Good architectural design treats the easement as a starting constraint, and structural engineering for custom homes resolves the footing detail before the drawings go for approval. The same applies to home extensions and additions, where the rear of the house often meets the easement first.

Getting consent to build over an easement

Four steps to building over an easement in Victoria, from title check to building permit

You can sometimes build on an easement, but only with the consent of the authority that holds it.

Regulation 130 of the Building Regulations 2018 requires the report and consent of the relevant service authority before a building is constructed over an easement vested in that authority (VBA Practice Note, Report and Consent, March 2023). The City of Yarra notes that a building surveyor cannot issue a building permit until any required report and consent has been obtained. That makes build-over consent part of the building permit process in Victoria, not something to sort out afterwards.

Who you apply to depends on the easement:

  • Council for stormwater drainage easements and council drains.
  • The water corporation for sewer and water assets. Under section 148 of the Water Act 1989, Yarra Valley Water’s consent is required to build a structure within one metre of its sewer or water infrastructure, or within its easement. Other Victorian water corporations run equivalent build-over processes.
  • Other parties with an interest, such as energy distributors, where their assets are involved.

Conditions are common. Depending on the authority, consent can require footings taken down to the level of the pipe, protection works, pipe upgrades, and a Section 173 agreement registered on title that records the consent and binds future owners. Glen Eira and Kingston both list these.

Timing varies by authority. The City of Yarra currently advises up to four weeks for report and consent applications, with longer periods possible. Glen Eira’s information sheet gives 10 working days after a complete application, or around 8 to 12 weeks where Council prepares a Section 173 agreement. Confirm current timeframes and allow for conditions before the permit stage.

During construction

Consent is only useful if the build follows it. On site, that means:

  • Confirming the actual pipe location before excavation, rather than relying on the plan alone.
  • Keeping the authority’s conditions with the approved drawings, so footing depths, clearances and protection works are built as approved.
  • Protecting pits and maintenance holes, and keeping them accessible throughout and after the build.
  • Watching the dates. Consents can lapse. Kingston’s are valid for 12 months from issue, so a delayed start may mean reapplying.

Clear project management keeps these conditions on the site program rather than in a forgotten email.

Can you remove or vary an easement?

Sometimes, but it is rarely quick, and it always involves the party that benefits from it. Land Use Victoria’s guide to removing easements and Victorian planning practice describe several routes:

  • Planning permit: clause 52.02 of the planning scheme, together with section 23 of the Subdivision Act 1988, covers creating, varying or removing an easement. This is the usual route where the change goes through council.
  • Abandonment by deed: a deed from the parties with the relevant interests can support an application to remove an abandoned easement under section 73 of the Transfer of Land Act 1958. A property lawyer should check the required parties, consents and registration steps.
  • Non-use: section 73(3) of the Transfer of Land Act 1958 treats proof of at least 30 years of non-use, to the Registrar’s satisfaction, as sufficient evidence of abandonment. Removal still requires an application and the statutory process; the easement does not simply disappear after 30 years.
  • Merger: where the same owner holds both the benefited and burdened land, the easement can be extinguished.

Additional consents may apply, depending on how the easement was created and who benefits from it. For a right of carriageway, section 73B of the Transfer of Land Act 1958 requires the Registrar to be satisfied that council has consented to its surrender. Obtain advice on the route and consents that apply to your title.

In practice, an easement holding live sewer or drainage pipes is very unlikely to be removed. Designing around it, or building over it with consent, is usually the realistic path. For anything beyond that, get property law advice.

Frequently asked questions

1. What does an easement mean in Australia?

An easement is a right for someone other than the owner to use part of a property for a set purpose, such as drainage, sewerage, utilities or access. The owner keeps ownership of the land, but cannot use the easement area in a way that interferes with that purpose. Easements are usually registered on title and shown on the plan, and they pass to each new owner when the property is sold.

2. What is the most common easement?

Drainage and sewerage easements are familiar examples on residential blocks in Melbourne, often along rear or side boundaries. Carriageway easements occur on battle-axe blocks and properties with shared driveways. Which type matters most depends on the services and access rights affecting your block. Check the title, plan and site services to establish what affects your land.

3. How do I know if my property has an easement?

Order a title search and the copy of plan through LANDATA, which show registered easements, their location, width and purpose. Then check the water corporation’s asset plan to see where pipes actually run. Be aware that implied easements under the Subdivision Act 1988 may not appear on a title search, so ask your builder or surveyor to look for drains and services on site.

4. Can you build on an easement?

Sometimes. Building over an easement needs the report and consent of the authority that holds it, under regulation 130 of the Building Regulations 2018, and the building permit cannot be issued until you have it. Lighter structures such as carports, pergolas and decks are more often approved than habitable rooms, and conditions such as deeper footings or a Section 173 agreement are common.

5. Can I put a pool or shed on an easement?

A shed is often possible with consent, subject to size and footing conditions. A pool is much harder. The City of Kingston, for example, generally refuses swimming pools, spas and their equipment over easements, while it often consents to sheds, garages and carports with plans. Check the rules of the council or water corporation that holds your easement before you design.

6. Who maintains an easement?

The owner of the land generally keeps the surface tidy, as with the rest of the block, while the authority or party that holds the easement is responsible for its own pipes and infrastructure. Authorities need access for maintenance and repairs, which is why pits and maintenance holes must stay clear. Responsibilities can differ between authorities and private easements, so check with the holder before carrying out works.

Plan around the easement early

The easier builds are the ones where the easement is found on day one and the design works with it, with consents lodged well before the permit stage. If you are planning a new home, extension or knock down rebuild on a block with an easement, book a pre-construction consultation with ROMAAC Group and we will review your title, plan and site constraints before design begins.

This article is general information about easements in Victoria and is not legal advice. Requirements differ between councils and water corporations. Check with the relevant authority and obtain property law advice for your situation.

Vector (8)
Explore expert tips and trends in premium construction and architectural design.
Get In Touch
Get In Touch
Arrow
CHECKOUT OUR LATEST BLOG POSTS
November 13, 2026
Queenslander House Guide: Features, History and Modern Queenslander Designs
This is some text inside of a div block.
November 13, 2026
Cost Plus Contract vs Fixed Price: Costs, Risks and Differences in Victoria
This is some text inside of a div block.
November 13, 2026
Raked Ceiling Designs: Benefits, Costs and Comparison With Vaulted Ceilings
This is some text inside of a div block.